Scope of work
Phase 1: design and construction of the concrete structure using the top-down method. Phase 2: supervision of the shell and finishing works.
Project data
| Location | Saadat Abad, Tehran |
|---|---|
| Excavation depth | 24 m |
| Structural system | Concrete frame |
| Floors above ground | 8 |
| Basement levels | 5 |
| Gross floor area | 8,000 m² |
| Construction period | 15 months |
| Client | Avest Group |