Tehran · 22 m deep · 5 basements · Concrete frame

Titanium Commercial & Office Complex

Titanium Commercial & Office Complex – top-down construction by Irantopdown

Scope of work

Fabrication and installation of precast concrete columns to stabilize one side of the site using the top-down method, in partnership with Pibaan.

Project data

Location Qazvin Street, Tehran
Excavation depth 22 m
Structural system Concrete frame
Floors above ground 6
Basement levels 5
Site area 3,000 m²
Construction period 3 months

Similar site?

We design and build the whole job.

Geotechnical model, precast columns and the finished frame, from one team. Your first consultation is free.