Scope of work
Phase 1: top-down structural and geotechnical design, plus fabrication and installation of precast concrete columns. Phase 2: construction of the concrete structure using the top-down method.
Project data
| Location | Vanak, Tehran |
|---|---|
| Excavation depth | 20 m |
| Structural system | Concrete frame |
| Floors above ground | 11 |
| Basement levels | 6 |
| Gross floor area | 14,000 m² |
| Site area | 1,300 m² |
| Construction period | 22 months |
| Client | Eng. Moeini |