Scope of work
Fabrication and installation of precast concrete columns using the top-down island method.
Project data
| Location | Vardavard, Tehran |
|---|---|
| Excavation depth | 12 m |
| Structural system | Concrete frame |
| Floors above ground | 8 |
| Basement levels | 3 |
| Gross floor area | 48,730 m² |
| Site area | 4,500 m² |
| Construction period | 4 months |
| Client | Tehran City Council Housing Cooperative |